A Timeline of Milestones

Here’s how the project came together:

  1. December 7, 2023Lunch & Learn with CIMA+
  2. February 24, 2024Visited Canmore WWTP to review opportunity
  3. September 9, 2024Visited another local Neutralox installation
  4. September 16, 2024First budget proposal provided
  5. October 25, 2024Received Air Quality Sampling Analysis Report
  6. November 14, 2024Received order for equipment
  7. April 17, 2025Equipment arrived onsite
  8. June 25, 2025Equipment start-up
  9. August 5, 2025Equipment commissioning completed